Road Construction Update - South Hook Street and Harbor Lane
Road Construction Update 12-23-2024
Road work in Harbor Grove is coming along nicely!
- Beginning on December 30th, and finishing up December 31st . McMahon Contracting will pour concrete on the eastbound lane up to the entrance of Harbor Grove. Preparation of the westbound lane will begin soon after the concrete has cured around 7 days.
- Attached is a baseline schedule that McMahon Contracting has put together for Harbor Lane, Hook Street & Garth Lane. As always, weather conditions could create some havoc in the timeline! Thank you again for your patience as we look forward to new roads and sidewalks.