Road Construction Update 12-23-2024

Road work in Harbor Grove is coming along nicely!

 

  • Beginning on December 30th,  and finishing up December 31st . McMahon Contracting will pour concrete on the eastbound lane up to the entrance of Harbor Grove. Preparation of the westbound lane will begin soon after the concrete has cured around 7 days.

 

  • Attached is a baseline schedule that McMahon Contracting has put together for Harbor Lane, Hook Street & Garth Lane.  As always, weather conditions could create some havoc in the timeline! Thank you again for your patience as we look forward to new roads and sidewalks.

 

 