Point Vista road northbound from Stamford to Turbeville has been completed with the exception of the private driveways and the drainage crossing. The drainage area will have new 42” rcp’s installed by Friday to facilitate drainage from the new home development. Beginning April 3, the west side of Point Vista or Southbound Point Vista will be milled and prepared for road stabilization.
Road stabilization is complete on the east side of Point Vista Road at the intersection as well as the westbound portion of Turbeville. Local concrete plants have notified the contractor they are on will call for concrete. Possible concrete pours will take place Friday pending weather and the availability of concrete.